NetInsight Page TagReady To Roll Existing Modular Units Vanguard Modular Building Systems
About Us
Why Modular?
Modular Solutions
Commercial
Education
GSA
Government
Corrections
Commercial Case Studies
Contact Us
Healthcare/Medical
Worship
Ready To Roll Solutions
Green Buildings
Sales Locator
Schiavi Leasing Corporation
Home
 
Corrections Facility Case Studies

York County Jail (Phase 2)
Alfred, ME

photo

Challenge: “Phase 2” was an addition to “Phase 1”, a 30 bed modular
cellblock completed in 2001. Because of severe overcrowding, additional cells could not wait for the new, permanent jail to be completed.

Modular Solution: After exploring many options, cost and logistics led to a modular solution with 3410 sq. ft. of medium security cell space and 2898 sq. ft. of Administrative/Program space. This 60 bed facility was constructed with 30 cells, day space, interview space, bathrooms and officer’s observation and control station. It was connected to the Phase 1 building with a site-built connector. It joins a Schiavi supplied 42' x 69' office complex/program building with offices, bathrooms, kitchenette, reception and large open areas. When the new permanent facility is ready, Phases 1 and 2 will become a required Pre-Release Center.

Project Schedule:
Date of award April 3
Site construction/building drawings submitted May 8
Site work begins June 20
Modular building manufacturing completed June 20
Modular building delivered June 25 (Program Bldg.)
June 28 (Cell Block Bldg.)
Substantial setup completed August 2
Occupancy August 8
From Start to Finish 127 Days
 
Download PDF of this Case Study (includes Floor Plan)
 
128 Bed Mininum Security Dorm
Charleston County, SC
photo

Challenge: Due to severe overcrowding additional bed space was needed quickly. In addition the available site was constrained by existing site conditions: a fence at the property line on the North end of the site,
by an existing structure on the South, by a fence and roadway on the East and by another existing structure on the West, making access very difficult and Public Utilities needed to be relocated to use the site.

Modular Solution: After determining the available footprint, a single story structure comprised of 16 modular units, (15,000 sq. ft.), was designed to fit the available space. The new structure was connected to an existing structure with a covered/fenced walkway. The facility has a backup generator capable of supplying all electrical needs for 3 days without refueling. Also CCTV, PA/Intercom, IRT Man down, Electronic door controls, electronic lighting controls and Video Visitation were incorporated. Connection to the existing Central Security Control System was provided along with key features being controlled via a touch pad PC. An existing public sanitary sewer was relocated to accommodate the new structure.

Project Schedule:
Notice of Award May 15
Notice to Proceed June 4
Engineering/Drawings June 4 10 Aug 15
Permitting July 5
Site work begins July 18
Foundation Starts August 20
Modular building delivered September 12
Set Modular Building September 21
Trim out of Modulars September to December
Utility Hookups September to December
Substantial setup completed December 28
Occupancy January 5
From Start to Finish 235 Days
 
Download PDF of this Case Study (includes Floor Plan & Additional Photos)
 
Medium Security Pre-Trial Youth Detention Facility
Massachusetts
photo

Challenge: A leading human services provider in Massachusetts needed a medium security pre-trial, youth detention facility to house its’ program for 20 juvenile offenders. The state of Massachusetts awarded the
project with a significantly shortened delivery schedule.

Modular Solution: Vanguard Modular Building Systems delivered a complete turnkey solution including all the necessary electronic safety and surveillance. Electronic door strikes and security grates were installed on all doors & windows with main panel individual locking capabilities and tied to the alarm panel to meet life safety standards. Fire alarms, sprinklers and electrical systems were all housed in a detached build- ing outside the secured, fenced area to allow for ease of access for any emergency responders. Vanguard Modular completed the project in 175 days providing the required housing on time.

Project Schedule:
Date of signed contract March 19
Site construction/building drawings submitted June 13
Site work begins July 10
Modular building manufacturing completed June 24
Building permit issued July 11
Substantial setup completed August 3
Occupancy September 10
From Start to Finish 175 Days
 
Download PDF of this Case Study (includes Floor Plan & Additional Photos)
 
PADOC Correctional Facilities
Pennsylvania
photo

Challenge: Overcrowding at Correctional facilities in Pennsylvania prompted the PADOC to turn to modular solutions for an expedient housing solution. The facilities were at four different locations across Pennsylvania and all with varying site conditions.

Modular Solution: Vanguard Modular Building Systems furnished and installed minimal security housing facilities, totaling over 57,000 sq. ft. The four projects ran concurrently to address housing needs for 150 inmates at each of three locations: SCI-Laurel Highlands, SCI-Pinegrove, SCI-Muncy and housing for 300 at the SCI-Retreat location. Each facility consisted of double bunk dormitory style housing with individual inmate cable TV. The dormitories included full bathroom and laundry facilities with epoxy coated concrete floors for durability. Security Control Systems were located at the guard stations and full sprinkler system and climate control installed. A large, dayroom with adjacent private counseling offices
were incorporated into the design.

Project Schedule:
Component Laurel Highlands Pine Grove Retreat Muncy
Notice of award for first location Aril 30 April 30 - May 29 April 30 - May 29 July 25
Engineering/Drawings April 30 - May 29 April 30 - May 29 May 1 - May 30 July 25 - Sept 9
Permitting July 16 -
Aug 24
July 16 - Aug 23 July 16 - Aug 23 Aug 24 - Oct 4
Site Work Starts May 29 -
July 3
July 9 -
Aug 27
Oct 1 -
Nov 7
Oct 5 -
Nov 30
Foundation Starts Jun 25 -
July 3
July 9 -
July 17
Oct 4 -
Oct 18
Oct 5 -
Oct 23
Delivery of Modular Building Aug 24 -
Aug 30
Sept 10 - Sept 27 Oct 29 - Nov 15 Nov 19 - Dec 4
Set Modular Building Oct 9 -
Oct 26
Nov 26 - Dec 7 Nov 26 - Nov 30 Dec 4 -
Dec 7
Trim out of Modulars Oct 9 -
Oct 26
Dec 10 - Dec 17 Dec 3 -
Dec 18
Dec 7 -
Feb 1
Utility Hookups Oct 29 -
Nov 5
Dec 10 - Jan 18 Dec 3 -
Jan 11
Dec 20 - Feb 15
Substantial Completion Dec 10 Feb 15 Feb 28 Mar 14
Occupancy Feb 11 May 6 Apr 30 May 2
Start to Finish 286 days 372 days 365 days 279 days
 
Download PDF of this Case Study (includes Floor Plan & Additional Photos)
 
 
Proud Member of the Modular Building Institute
National Association of Home Builders
GSA Contract Holder
 
1-877-GET-VMBS
 
Vanguard Modular Building Systems Headquarters:
3 Great Valley Parkway, Suite 170
Malvern, PA 19355
 
About Us | Why Modular? | Modular Solutions | Ready to Roll Solutions  | GSA | Sales Locator
The Vanguard Modular Advantage | Schiavi Leasing Corp. | Contact Us | Home
 
       
   
Stay Informed! Sign up for FREE eUpdates.
 
 
       
    © 2009 Vanguard Modular Building Systems, LLC. All Rights Reserved.