Amherst College Dormitories
Amherst, Massachusetts |
 |
“We were surprised by the
flexibility Vanguard Modular
demonstrated in adapting their construction schedule to accommodate
the
restrictions imposed by other activities on campus.”
Peter Root
Project Manager,
Amherst College
Amherst, Massachusetts |
| |
Challenge:
Swelling enrollments and limited time required quick
construction of two new dormitories for the fall. Each building
needed to hold 50 students, with full bathroom facilities and
standard dorm amenities such as cable TV, high-speed internet,
climate control and sprinklers in each room. They needed to be
temporary additions, for use during renovations to existing dorms,
but still
blend with the campus.
Modular Solution:
Modular
dormitory buildings solved both the space and time requirements
at Amherst.
The buildings were constructed
at the factory for the most efficient delivery schedule.
They were upgraded with 2x6 wall and floor construction, extra
insulation
and
vinyl siding to blend with other buildings.
Site work began in April and was completed in August, in
time for fall semester students to move in. |
| |
| Project Schedule: |
| Contract signed |
March 15 |
| Site work begins |
April 1 |
| Modular building manufacturing completed |
May 1 |
| Modular building delivered |
May 30 |
| Substantial setup completed |
July 24 |
| Occupancy |
August 7 |
| From Start to Finish 145 Days |
|
| |
| Download Project
PDF (File size 2.4 MB) |
| |
| |
Hall-Dale Elementary School
Farmingdale, Maine |
 |
"We were favorably impressed with the quality construction
of our
temporary school building. Schiavi Leasing made it easy to quickly
house our students and responded in a timely manner to all issues.
We were even able to incorporate some of our own ideas into the
building plans.
If the need arose, we would be sure to contact Schiavi in the future."
Nora
Murray
Superintendent
Hall-Dale Elementary School
Farmingdale, Maine |
| |
Challenge: The expanding population
and desperate need for renovation of the 50-year old school created an immediate need
for over 16,000 sq. ft. of elementary school space for 200 students.
The Schiavi Leasing technical team needed to solve this crisis,
on time and on budget.
Modular Solution: The solution was
a complete turnkey project - including excavation, foundation,
modular
building design and construction,
installation, landscaping and drainage, electrical, plumbing,
fire alarm, data and communications wiring, a complete sprinkler
system
throughout the building, plus a heated connecting corridor to
the adjacent school. |
| |
| Project Schedule: |
| Contract signed |
June 21 |
| Site construction/building drawings submitted |
June 30 |
| Site work begins |
August 30 |
| Modular building manufacturing completed |
September 7 |
| Modular building delivered |
September 19 |
| Occupancy |
October 10 |
| From Start to Finish 110 Days |
|
| |
| Download
Project PDF (File size 136 kb) |
| |
| |
Pentucket Regional School District
West Newbury, Massachusetts |
 |
“Vanguard Modular exceeded my expectations in every area
and
helped us meet a time frame that seemed impossible. If the need
were to arise. I would have no
hesitation about contacting
Vanguard again.”
Richard O’Shea
Business Manager
Pentucket Regional School District
West Newbury, Massachusetts |
| |
Challenge: To accommodate a rapidly growing student
population, Pentucket Regional School District required four 900
sq. ft.
classrooms to be immediately added to their existing building.
Each classroom required fire alarms and comprehensive data and
communications
wiring.
Modular Solution: Vanguard Modular delivered a complete turnkey
solution – including
excavation,
foundations, modular building design and construction, installation,
matching existing school floor level and brick exterior, landscaping
and drainage, and providing compatible equipment and connections
for existing fire alarm, intercom and computer data lines. The
rooms were completed on time and at a fraction of the cost of traditional
construction. |
| |
| Project Schedule: |
| Date of award |
April 3 |
| Site construction/building drawings submitted |
May 5 |
| Site work begins |
June 30 |
| Modular building manufacturing completed |
July 28 |
| Modular building delivered |
August 2 |
| Substantial setup completed |
August 31 |
| From Start to Finish 150 Days |
|
| |
| Download
Project PDF (File size 112 kb) |
| |
| |
Trinity Episcopal School
Charlotte, North Carolina |
 |
“Vanguard Modular’s understanding of the entire process,
from building permit to certificate of occupancy, gave us confidence
that the school would be ready in time. They delivered everything
and finished the job to our complete satisfaction.”
Peter
J. Conway
Board or Advisors
Trinity Episcopal School
Charlotte, North Carolina |
| |
Challenge: A temporary
school was needed immediately while the community raised funds
for a permanent school building.
Specifications for the entire building needed to be developed by
Vanguard Modular and working with the architect on the site plan
was also a requirement.
Modular Solution: Vanguard Modular delivered
a complete turnkey solution. Vanguard Modular was in charge of
the building construction as well
as the necessary electrical, plumbing and mechanical permits. Vanguard
Modular’s role included building design and construction,
site preparation, installation, decking, equipment and connections
for
the fire alarm, and all pre-wiring for the data and communications
systems. Even with a re-zoning issue, the time from delivery to
operational completion was just six weeks. |
| |
| Project Schedule: |
| Date of signed contract |
March 23 |
| Site construction/building drawings submitted |
March 30 |
| Site work begins |
May 9 |
| Modular building manufacturing completed |
June 27 |
| Building permit issued |
July 7 |
| Modular building delivered |
July 12 |
| Substantial setup completed |
August 7 |
| Occupancy |
August 23 |
| From Start to Finish 152 Days |
|
| |
| Download
Project PDF (File size 132 kb) |
| |
| |
Just want more information about your specific needs
for a modular solution for your Education facility?
Contact Form
Find Your Local Sales Representative |
| |